Costerfield Operations Brunswick Underground Contract
Scope of Works
Providing underground development mining services including:
- Horizontal development works of some 1200m at 4.5mW X 5.5mH, 1:23Up
- Incline and decline development of approximately 2500m of up to 5.5mW X 5.5mH, 1:7
- Level access, stockpile development and vent access approximately 1300m at 5mW X 4.8mH, 1:50Up
- Haulage of all capital development materials to surface waste stockpiles utilizing a CAT AD45
Project Highlights
- Zero Lost Time Injury
- RUC mining’s first mechanized mining venture to the Eastern States of Australia
- Averaging 188m per month of fully supported development in a single heading with a Sandvik DD421-60 Jumbo, over 10 consecutive months, peak performance of 217m in a single month with 4 man crews