Scope of Works

Providing underground development mining services including: 

  • Horizontal development works of some 780m at 4.5mW X 5.5mH, 1:23Up

  • Incline development of approximately 1100m at 4.5mW X 4.8mH, 1:7Up

  • Level access, stockpile development and vent access approximately 700m at 5mW X 4.8mH, 1:50Up

  • Haulage of all capital development materials to surface waste stockpiles utilizing a new AD30 CAT

Project Highlights

  • Zero Lost Time Injury

  • RUC mining’s first mechanized mining venture to the Eastern States of Australia

  • Averaging 188m per month of fully supported development in a single heading with a Sandvik DD421-60 Jumbo, over 10 consecutive months, peak performance of 217m in a single month with 4 man crews