COSTERFIELD OPERATIONS BRUNSWICK UNDERGROUND CONTRACT
STATUS: CURRENT
Client: Mandalay Resources
Location: 50km SE of Bendigo VIC
Contract Duration: 24 Months
Safety Statistics: 0.0 LTIFR
Scope of Works
Providing underground development mining services including:
-
Horizontal development works of some 780m at 4.5mW X 5.5mH, 1:23Up
-
Incline development of approximately 1100m at 4.5mW X 4.8mH, 1:7Up
-
Level access, stockpile development and vent access approximately 700m at 5mW X 4.8mH, 1:50Up
-
Haulage of all capital development materials to surface waste stockpiles utilizing a new AD30 CAT
Project Highlights
-
Zero Lost Time Injury
-
RUC mining’s first mechanized mining venture to the Eastern States of Australia
-
Averaging 188m per month of fully supported development in a single heading with a Sandvik DD421-60 Jumbo, over 10 consecutive months, peak performance of 217m in a single month with 4 man crews