STATUS: COMPLETE
CADIA CRUSHED ORE BIN -
VENT SHAFT
Client: Newcrest Mining Ltd
Location: Cadia East - Orange, NSW
Contract Duration: 3 months
Safety Statistics: 0.0 LTIFR
Scope of Works
Excavation and support of a 6.5m dia x 34m deep Crushed Ore Bin and civil construction and installation of bin and rail liners, including:
-
Engineering, Design and Methodology developed by RUCC
-
Excavation and construction of shaft collar – 7mW x 7mL x 2mD
-
Strip and Line crane sink to -34m depth and concrete line to a finished diameter of 6.5m
-
Installation of temporary ground support through 8m breakthrough round
-
Installation of first 3 x bin liners (flanged) at combined weight of ~25t utilising RUC Mining and Wilshaw designed supporting frame installed on the shaft collar
-
Place scribing and concrete pouring to lock bin liners in place
-
Installing remaining bin liners in 3m lifts while pouring concrete infill between liner and shaft wall
-
Installing rail mats inside bin liners and weld nuts to lock in place