Portal development works of Evolution Mining’s Edna May Project, including:

  • Installing Geobrugg mesh along the pit wall above the portal location
  • Stabilising the immediate area around the portal. This involved excavating a key-way, fibrecreting and installation of gewi bars, cable bolts and spiling bars
  • Developing portal access to breakthrough into existing decline development
  • Rehab of portal/decline intersection and rehab of 100m of decline
  • Installation of the underground power supply
  • Dry hire of fixed equipment
  • Evolution Mining | Edna May Mine
  • 0

Project Highlights

The Project:

  • Had no reportable injuries
  • Was completed under budget
  • Was completed ahead of schedule